| BIECCO LAWRIE LIMITED | ||||||||||||||||
| DETAILS OF CONTRACTS CONCLUDED DURING THE MONTH OF MAR'2008.(VALUE > Rs.50,000/-) | ||||||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 |
| Tender No. | Item/Nature of work | Mode of Tender Enquiry | Date of Publication of NIT | Type of Bidding (Single/Two Bid System) | Last date of receipt of tender | Nos of tenders recd. | Nos. and names of parties qualified after technical evaluation. | Nos. and names of parties not qualified after technical evaluation. | Whether contract awarded to lowest tenderer/ evaluated L(1). | Contract No. & Date | Name of Contractor | Value of Contract (Rs.lacs) | Scheduled date of completion of supplies. | Actual date of start of work | Actual date of completion | Reasons for dealys if any |
| PROJ/DVC-WB/011 | 1.Construction of Store room for equipment with corrogated tin sheet and other anchoring materials,Brickflat soaling (BFS) in floor with supply of material at Durgapur. | Limited | 28-Dec-07 | Single | 4-Jan-08 | 3 | 1) Maa Durga Enterprise 2) Bhutai Enterprise 3) The Globalisers | NIL | Lowest tender (L1) | BLL/PROJ/DVC-WB/ORD/009, 01.03.08 | Maa Durga Enterprise | 115056 | 7 days from the date of placement of order. | 5-Feb-08 | ||
| 2.Construction of Store room for equipment with corrogated tin sheet and other anchoring materials,Brickflat soaling (BFS) in floor with supply of material at Barjora. | ||||||||||||||||
| PROJ/DVC-WB/014 | 1) Supplying, Fabricating & Galvanising various switchyard structures with contractors own tools & tackles, crane & labour complete including bolted and / or welded connections with G.I. Bolts, nuts, washers, etc., complete as per drawings specifications & directions for CT , Isolator, Bus Support at different Substation in West Bengal | Limited | 14-Jan-08 | Single | 4-Feb-08 | 3 | 1)M/s Ashoka Tools Pvt. Ltd 2) M/s Holymoon &Co 3) M/s Sunsteel industries Pvt. Ltd. | NIL | Lowest(L1) | BLL/PROJ/DVC-WB/ORD/010, DT. 07/03/08 | M/s Holymoon & Co. | 3507754 | For Item no-1, delivery within three months & for item no-2, delivery within 15 days from the date of receipt of order. | 7-Mar-08 | ||
| 2) 50mm x 6mm G.I. Flat For earthing of structures and equipments. | ||||||||||||||||
| ENQ/BLL/2008-09/1 | Oracle Database Server Enterprise Edition 10g | Limited | 11.03.2008 | Single | 18.03.2008 | 3 | Tata Consultancy Services Limited, M/s Supertech Enterprise, Chabria Infotech Pvt. Ltd. | NIL | L1 | SYS/CON/2007-2008/10 Dated 25.03.2008 | Tata Consultancy Services Limited | 23.65795 | within 8 weeks | |||
| ENQ/BLL/2008-09/2 | Blade Server with OS Red Hat Linux | Limited | 12.03.2008 | Single | 18.03.2008 | 3 | Cal - Forms, HCL Infosystems Limited, R.B.Enterprise | NIL | L1 | IMCMP/C/2007-2008/11 dated 24.03.2008 | HCL Infosystesm Limited | 10.14 | within 4 weeks | |||
| BLL/522 | PVC BARRIER/COVER | LIMITED | 12-Feb-08 | SINGLE | 20-Feb-08 | 2 | N/A | N/A | L(1) | HR/43896, DT.3.3.08 | MODOPLAST CO. | 910890.24 | SEP'08 | |||
| BLL/525 | SILICONE GREASE/METROARK 17-COMPOUND. | LIMITED | 19-Feb-08 | SINGLE | 28-Feb-08 | 3 | N/A | N/A | L(1) | HR/43895, DT.1.3.08 | WACKER METROARK CHEMICALS | 162489.60 | DEC'08 | |||
| BLL/526 | AL.BRONZE COMP | LIMITED | 19-Feb-08 | SINGLE | 25-Feb-08 | 1 | N/A | N/A | L(1) | HR/43901, DT.3.3.08 | STANDMECH ENGINEERING | 152880.00 | SEP'08 | |||
| BLL/527 | PACKING WOOD/CRATE | LIMITED | 22-Feb-08 | SINGLE | 26-Feb-08 | 2 | N/A | N/A | L(1) | HR/43894, DT.1.3.08 | HASSAN BROTHERS | 69472.00 | DEC'08 | |||
| BLL/528 | FABRICATED M/C.COMPONENTS | LIMITED | 6-Mar-08 | SINGLE | 12-Mar-08 | 2 | N/A | N/A | L(1) | HR/43988, DT.19.3.08 | T.M.ENGINEERING WORKS | 161558.80 | SEP'08 | |||
| ENQ/0424 | Repairing of ER Shop Roof at MBW | LIMITED TENDER | 31.01.08 | TWO | 29.02.08 | 7 | 1) Walls & Roofs, 2) Apex Construction, 3) M C Construction, 4) S K Ghosh & Company, 5) Kalpana Traders, 6) Duttcon and 7) Bhattacharya Construction | 1) Duttcon & 2) Bhattacharya Construction | L1 | AD/HR/2119/SER DT. 08.03.08 | M/S M C Construction | 4.09 | May-08 | 18.03.08 | 60 DAYS | |
| CN/PUR2/004:08 | Hired Security Guard (Unarmed) | LIMITED TENDER | 26.02.08 | Single | 13.03.08 | 3 | 1) Scion Security And Allied Services, 2) BGS Sec & Allied Services & 3) Sarvodya Security Services | L1 | AD/HR/2128/SEC DT. 28.03.08 | Sarvodya Security Services | 14.38 | YEARLY | YEARLY | |||
| CN/PUR2/005:08 | Hired Security Guard (Armed) | LIMITED TENDER | 25.03.08 | Single | 27.03.08 | 1 | Sarvodya Security Services | L1 | AD/HR/2131/SEC DT. 29.03.08 | Sarvodya Security Services | 0.65 | YEARLY | YEARLY | |||
| 9521/AS | MFG OF SILVER BEARING COMMUTATOR OF 171 SEG. | LIMITED | 13-02-08 | SINGLE | 20/02/08 | 3 | 1.THE BENGAL COMMUTATOR WORKS. 2.COMMUTATOR MFG. 3.SAHNEY COMMUTATORS PVT. LTD. | NIL | L-1 | MB/11714/ER dt.05-03-08. | SAHNEY COMMUTATORS PVT. LTD. | 107976.96 | WITHIN 6 WEEKS. | |||
| 9567/AS | DGC COPPER CONDUCTOR 6.45 + -0.05MM X 6.45 + - 0.05MM. | LIMITED | 26-02-08 | SINGLE | 03/03/08 | 2 | 1.PARAMOUNT CONDUCTORS LTD. 2.SAGUN COPPER CONDUCTORS(P) LTD. | NIL | L-1 | MB/11717/ER dt.06-03-08. | PARAMOUNT CONDUCTORS LTD. | 105757.43 | WITHIN 15 DAYS. | |||
| 9455/AS | MFG OF NEW COMMUTATOR FOR 500 H.P. ARMATURE. | LIMITED | 25/01/08 | SINGLE | 31/1/2008 | 3 | 1.THE BENGAL COMMUTATOR WORKS 2.DOLPHIN ELECTRIC(P) 3.SAHNEY COMMUTATORS PVT. LTD. | NIL | L - 1 | MB/11722/ER dt.08-03-2008. | DOLPHIN ELECTRIC ( INDIA ) | 359470 | WITHIN 6 WEEKS | |||
| 9454/AS | MFG OF NEW COMMUTATOR FOR 500 H.P. ARMATURE. | LIMITED | 25/01/08 | SINGLE | 31/1/2008 | 3 | 1.THE BENGAL COMMUTATOR WORKS 2.DOLPHIN ELECTRIC(P) 3.SAHNEY COMMUTATORS PVT. LTD. | NIL | L - 1 | MB/11723/ER dt.08-03-2008. | DOLPHIN ELECTRIC ( INDIA ) | 359470 | WITHIN 6 WEEKS | |||
| 9407/JC | LAB. CH.FOR REWINDING OF ARM & UNDERCUTTIUNG COMM. | LIMITED | 4/2/2008 | SINGLE | 12/2/2008 | 4 | 1.B.P.ENTERPRISES PVT. LTD. 2.EMIC MOTORS (P) LTD. 3.MA-KALI ENGINEERING WORKS. 4.PREMIER DIESELS PVT. LTD. | NIL | L - 1 | MB/11724/ER Dt.10-03-08. | ESDEE ELECTROMILL PVT. LTD. | 68208.00 | WITH IN 10 DAYS. | |||
| 9491/JC | MFG. OF ARMATURE SHAFT | LIMITED | 2/2/2008 | SINGLE | 20-2-2008 | 3 | 1.ESDEE ELECTROMILL PVT. LTD. 2.J.S.INDUSTRIES 3.MA-KALI ENGINEERING WORKS | NIL | L - 1 | MB/11725/ER Dt.10-03-08. | J.S.INDUSTRIES | 75296.00 | WITH IN 21 Days | |||
| 9396/JC | LAB. CH. FOR FORMING OF ARMATURE COILS. | LIMITED | 3/1/2008 | SINGLE | 10/1/2008 | 3 | 1.BABCO ELECTRICALS 2.CHILLMECH TECHNO PVT.LTD. 3.MA-KALI ENGINEERING WORKS. | NIL | L - 1 | MB/11726/ER Dt.10-03-08. | MA-KALI ENGG. WORKS | 50000.00 | WITH IN 14 DAYS. | |||
| 9593/AS | EN DGC COPPER COND AS PER IS 10114. ( 1.4 X 6.3 )M2 | LIMITED | 06-03-08 | SINGLE | 12/03/08 | 2 | 1.PARAMOUNT CINDUCTORS LTD. 2.SAGUN COPPER CONDUCTORS(P) LTD. | NIL | L - 1 | MB/11744/ER Dt.18-03-08. | SAGUN COPPER CONDUCTORS(P) LTD. | 61318.00 | WITH IN 15 DAYS. | |||
| 9407/JC | LABOOUR CH. FOR REWIND -ING OF ARM & UNDERCUTTING COMM. | LIMITED | 04-02-08 | SINGLE | 12/02/08 | 2 | 1.MA-KALI ENGINEERING WORKS. 2.PREMIER DIESELS PVT. LTD. | NIL | L-1 | MB/11740/ER Dt.12-03-08 | MA-KALI ENGINEERING WORKS. | 56400.00 | 10 DAYS FOR EACH ARMATURE FROM THE DATE OF RECEIVE ARMATURE. | |||
| 9576/AS | LABOUR CHARGES FOR REPAIRING & REMICA OF OLD COMM. | LIMITED | 27-02-08 | SINGLE | 03/03/08 | 2 | 1.THE BENGAL COMMUTATOR WORKS. 2.DOLPHIN ELECTRIC (INDIA). | NIL | L-1 | MB/11749/ER Dt.19-03-08. | THE BENGAL COMMUTATOR WORKS. | 104000.00 | WITHIN 45 DAYS. | |||
| 9590/AS | MICAPAG EP FOLIUM SAMICA THERM WRAPPER 0.18 X 1000 X M | LIMITED | 06-03-08 | SINGLE | 13/03/08 | 2 | 1.AGATE ELECTRO INSULANTS (P) LTD. 2.M/S ISOVOLTA (INDIA) PVT. LTD. | NIL | L - 1 | MB/11752/ER Dt.20-03-08. | M/S ISOVOLTA (INDIA) PVT. LTD. | 209777.00 | ON REQUEST. | |||
| 9592/AS | MICAPAG SAMICA FLEX TAPE 20MM X 50 MTR X 0.16MM | LIMITED | 07-03-08 | SINGLE | 14/03/08 | 3 | 1.AGATE ELECTRO INSULANTS(P) LTD. 2.M/S ISOVOLTA (INDIA) PVT.LTD. 3.LASHMANAN ISOLA (P) LIMITED. | NIL | L-1 | MB/11785/ER Dt.26-03-08. | AGATE ELECTRO INSULANTS (P) LTD. | 109437.50 | 300 ROLLS WITH IN 15 DAYS. BALANCE ON REQUEST. | |||
| 9594/AS | MFG. OF SILVER BEARING COMMUTATOR OF 171 SEG. | LIMITED | 07-03-08 | SINGLE | 12/03/08 | 3 | 1.THE BENGAL COMMUTATOR WORKS. 2.DOLPHIN ELECTRIC (INDIA). 3.SAHNEY COMMUTATOR. | NIL | L-1 | MB/11792/ER Dt.28-03-08. | SAHNEY COMMUTATOR P. LTD. | 106067.00 | WITH IN 15 DAYS. | |||
| 9580/JC | COPPER RING TOUNG TERM. CRIMPING SOCKET 150 SQ.MM | LIMITED | 29-02-2008 | SINGLE | 07-03-2008 | 1 | 1. SUNIL & CO. | NIL | L-1 | MB/11793/ER Dt.28-03-08. | SUNIL & COMPANY | 58113.00 | WITH IN 30 DAYS. | |||